Observing the attached PDM diagram, how many days would it take to execute the project beginning to end if items 6 & 7 combined were 10 weeks? (Assume 1 week =7 days)
The total number of weeks to execute the project from beginning to end is 17 weeks and 7 days.
The total number of weeks to execute the project from beginning to end is 18 weeks.
The total number of weeks to execute the project from beginning to end is 17 weeks and 6 days.
None of these
The total number of weeks to execute the project from beginning to end is 17 weeks and 5 days.
The correct answer is 17 weeks and 6 days to complete project beginning to end, critical path is items 1,2,3,4,6,7,9,10, &11 and a week is equivalent to 7 days. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.