The estimate for an activity's cost based on analysis of the worst-case scenario for the activity is called ____________________.
cP pessimistic
cM most likely
cO optimistic
Triangular distribution
This is a standard definition used in the PMBOK Guide under Project Cost Management under estimate costs process