A Construction company has a project to build a shed for Mr. Miller. The following are details, not in any order, which are required to complete the project once contract has been signed. You need to order each task appropriately into a PDM. 1. Put Roof on shed -2 Days and cannot start before frame is complete. 2. Clear and level land for base of shed _ 2 days _Start after contract 3. Acceptance of Shed by Mr. Miller -1Day 4. Build Shed Base/Floor -1 Day 5. Deliver Wood to site _Same Start as Clear and Level Land -1 day 6. Build Frame must start after Base Floor is complete _1 day 7. Attach walls and window once frame is complete _ 2 days 8. Door Installation _cannot start until walls/window installation complete _1 day 9. Put cement down for pad base/floor of shed _1 day, 2 days to cure before putting In base/floor Which is the correct order for this project?
2, 5, 9, 6, 4, 1, 7, 8, 3
2, 5, 9, 4, 6, 1, 7, 8, 3
1, 2, 3, 4, 5, 6, 7, 8, 9
2, 5, 4, 9, 6, 1, 7, 8, 3
2, 5, 9, 4, 6, 1, 7, 8, 3 is correct as it follows the proper ordering of construction. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.