A manager is planning a software project that involves multiple locations, with 25 team members. Four of them are testers. According to the auditing group, the addition of a QA professional is recommended, which will incur additional cost. The project manager is aware of the importance of communication, so they add extra communication channels. How many additional communication channels are introduced as a result of that organizational change in the project?
5
25
24
1
26*25/2 = 325, therefore, 325-300 = 25.