A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
Avoidance
Mitigation
Exploit
Transference
When you are hiring a third party to own risk, it is known as transference risk response. Transference is a strategy to mitigate negative risks or threats. In this strategy, consequences and the ownership of a risk is transferred to a third party. This strategy does not eliminate the risk but transfers responsibility of managing the risk to another party. Insurance is an example of transference. Answer: B is incorrect. The act of spending money to reduce a risk probability and impact is known as mitigation. Answer: A is incorrect. Exploit is a strategy that may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. Answer: D is incorrect. When extra activities are introduced into the project to avoid the risk, this is an example of avoidance.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.