Estimates are made of potential project schedule and cost outcomes listing the possible completion dates and costs with their associated confidence. This is the definition of what type of risk register update?
probabilistic analysis of the project
trends in quantitative risk analysis results
project documents updates
prioritized list of quantified risks
PMBOK 5th ed. p. 341