Harriet has a project that was scheduled for 10months. The Planning section took 2 months, The Execution phase took 6 months, and the final phase is still open. Harriet estimates that the project is 90% complete. What is the status of the project?
Undetermined
Behind Schedule
Ahead of Schedule
On Schedule
Let's first look at the data: So far 8months of planned value have been consumed on an 10month project. If the project is 90% complete, .9*10months =9months=EV. SV=EV-PV=9-8=+1. The correct answer shows that project is ahead of Schedule