If a previous project had 10 workers with five offices, using analogous estimating, how many offices are needed for 200 people?
100
40
200
This value cannot be calculated with the information given.
Analogous estimating involves comparison of a current project to a past, similar project. 10/5 =2 . 200/2 =100.