If VAC is Neutral and CPI is Exactly 1.0, then ________________________.

the project is negative on planned budget but positive on cost

the project is exactly on planned budget, but cost is higher then planned

the project is not on planned budget, but is on planned cost

the project is exactly on planned budget and cost

the project is off on planned budget and cost

Explanation

T52-Plan Cost Management ITTOs

Video Training

Train with Skillset and pass your certification exam. Faster. Guaranteed.

Directory

Skillset helps you pass your certification exam.

Contributions and Interactions
Practice Questions

Study thousands of practice questions that organized by skills and ranked by difficulty.

Contributions and Interactions
Personalized Training

Create a tailored training plan based on the knowledge you already possess.

Training Video Selector
Exam Readiness

Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.

Get A Free Skillset Account