Observing the attached PDM diagram, how many days increase would it take to put Items 4,6,&7 on critical path vs 4 & 5? (Assume 1 week =5 days)
You would need to add 3 weeks and 1 day to change 4,6,& 7 to cricital path vs. Item 4 & 5
None of these
You would need to add 2 weeks and 1 day to change 4,6,& 7 to cricital path vs. Item 4 & 5
You would need to add 1 week and 1 day to change 4,6,& 7 to cricital path vs. Item 4 & 5
You would need to add 2 weeks and 2 days to change 4,6,& 7 to cricital path vs. Item 4 & 5
The correct answer is 2weeks and 1 day to have 4,6, & 7 on critcal path rather than 4 &5. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.