Observing the attached PDM diagram, what is critical path to execute the project beginning to end? (Assume 1 week =5 days)
The correct answer to critical path from beginning to end is 1,2,3,4,6,7,12,13,14
The correct answer to critical path from beginning to end is 1,2,3,5,8,12,13,14
The correct answer to critical path from beginning to end is 1,2,3,5,8,12,13,15
The correct answer to critical path from beginning to end is 1,2,3,5,8,9,10,11,14
None of these
The correct answer to complete project beginning to end, critical path is items 1,2,3,5,8,12,13,14, and week is equivalent to 5 days. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.