The project above involves designing a product. Based on the project flow above, can the Raw materials be purchased any sooner than 1 week and if so which scenario below would contribute to that possibility?
There is no way to purchase raw materials any sooner than 1 week
None of these
The only way the raw materials could be purchased sooner would be if both the equipment purchases and product design were completed sooner
The only way the raw materials could be purchased sooner would be if the design completed earlier
This task has 2 dependencies, both having a minimum of 1 weeks lead time. Both of the dependencies would need to be completed sooner for raw materials to be purchased earlier. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.