Jeb knows that when planning a project the following conditions are historically valid. It usually takes 2 months to gather specifications, get alignment amongst key stakeholders, and draft initial plan. He also knows that during the holiday season most activities shut down during Thanksgiving/Christmas/New Years so project planning during this time of the year usually can elongate out planning to 4 months. If we start gathering specifications early enough before Halloween, we can typically cut our 4 month timeframe down to 3 months. Using 3 point estimating technique which of the answers below is the most likely outcome?
4 months
5.5 months
3 months.
3.75 months
The formula is as follows: Expected =(O+4M+P)/6 correct answer is (2+(3*4)+4)/6 = 3 months.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.