Jim knows that when planning a project the following conditions are historically valid. It usually takes 3 months to gather specifications, get alignment amongst key stakeholders, and draft initial plan. He also knows that during the holiday season most activities shut down during Thanksgiving/Christmas/New Years so project planning during this time of the year usually can elongate out planning to 5 months. If we start gathering specifications early enough before Halloween, we can typically cut our 5 month timeframe down to 4 months. Using 3 point estimating technique which of the answers below is the most likely duration when planning a project at the end of the year?
5.5 months
4 months
3.75 months
3 months
The formula is as follows: Expected =(O+4M+P)/6. 4 Months is correct as (3+(4*4)+5)/6 = 4 months.
(PMBOK 2013 Rev 5th Edition, pgs 170-171). If you make the assumption that you are planning during the Holiday time frame, otherwise the data is extraneous.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.