Kevin is project manager for a consulting company that specializes in the installation of food manufacturing equipment. One of his current projects is nearing the completion of the Direct and Manage Project Work process. Which of the following is an output he would only be concerned with as part of this process? (PMBOK 5th Edition pg 85)
Work performance data
Change Requests
Project document updates
Project management plan updates
Work Performance Data, the raw observations and measurements taken while activities are being performed to carry out project work, is only an output of the Direct and Manage Project Work process. Change requests, project management plan updates, and project document updates are all outputs of the Direct and Manage Project Work process, but are also outputs of other processes.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.