Lisa has a project that was scheduled for 8months. The Planning section took 1 month, The Execution phase took 5 months, and the final phase is still open. Lisa estimates that the project is 80% complete. What is the status of the project?
Undetermined
On Schedule
Ahead of Schedule
Behind Schedule
Let's first look at the data: So far 6months of planned value have been consumed on an 8month project. If the project is 80% complete, .8*8months =6.4months=EV. SV=EV-PV=6.4-6=+.4. The correct answer is A and shows that project is ahead of Schedule. (PMBOK 2013 Rev 5th Edition, pgs 217-225).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.