Skillset can help you prepare! Sign up for your free Skillset account and take the first steps towards your certification.
Nick has 3 projects, with the following conditions: Project 1 _ CPI=.95 & SPI =1.15 is inClosing Phase of Project, Project 2- CPI=1.05 & SPI=1.15 is in Execution phase of project, Project 3 _ CPI= 1.05 & SPI=1.0 is in Planning phase of project. Which of his projects, based on the CPI and SPI parameters alone has best position on schedule and cost?
None of the Projects
Project 3
Project 2
Project 1
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. Project 2 has best schedule and cost CPI/SPI.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.