Observing the attached PDM diagram, how many days would it take to execute the project beginning to end if we increase tem 7 to 10 days? (assume 1 week = 5 days)
The total number of weeks to execute the project from beginning to element 9 is 11 weeks and 4 days.
The total number of weeks to execute the project from beginning to element 9 is 11 weeks and 1 day.
The total number of weeks to execute the project from beginning to element 9 is 11 weeks.
The total number of weeks to execute the project from beginning to element 9 is 12 weeks.
None of these
The correct answer is 43 days to complete project beginning to end, critical path is items 1,2,3,4,5,8,9, &10 -7 is not on critical path until it reached 1wk and 3 days). (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.