Observing the attached PDM diagram, how many days would it take to execute the project beginning to end if we decrease item 5 to 10 days? (assume 1 week = 5 days)
The total number of days to execute the project from beginning to end is 49 days.
None of these
The total number of days to execute the project from beginning to end is 36 days.
The total number of days to execute the project from beginning to end is 46 days.
The total number of days to execute the project from beginning to end is 5 weeks and 9 days.
The correct answer is 36 days to complete project beginning to end, critical path is items 1,2,3,4,6,7,8,9, &10 -5 in no longer on critical path until as it is below combination of 4,6, & 7. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.