Observing the attached PDM diagram, how many days would it take to execute the project beginning to start of Item 8? (Assume 1 week =7 days)
The total number of days to execute the project from beginning to start of Item 8 is 48 days.
None of these
The total number of days to execute the project from beginning to start of Item 8 is 36 days.
The total number of days to execute the project from beginning to start of Item 8 is 46 days.
The total number of days to execute the project from beginning to start of Item 8 is 43 days.
The correct answer is None of These because you are going ONLY to the start of item 8. What PDM diagram?
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.