5 weeks & 4 days
9 weeks & 4 days
7 weeks
8 weeks & 2 days
9 weeks & 4 days is incorrect as it is total duration of project. 5 weeks & 4 days is incorrect as it is duration of tasks 1-4 and 6-7; 5 is actual critical path. 7 weeks is correct as tasks 1-3=3 weeks & 1 day, task 5 = 3 weeks & 4 days for a total of 7 weeks. 8 weeks and 2 days is incorrect as it is the sum of tasks 1-3, 5, and 8 = 5 unless task 6-7 are increased. (PMBOK 2013 Rev 5th Edition, pgs 177-180).