Jeremiah has 3 projects, with the following conditions: Project 1 _ CPI=.8 & SPI =.9 Project 2- CPI=1.1 & SPI=.8 Project 3 _ CPI= 1.0 & SPI=1 Which of his projects does he need to ask for support to get back on track?
Project 1
Project 2
None of these
Project 3
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. While one could surmise that it would be Project 1 as it is behind in both schedule and planned cost; there is not enough information to make a decision. We do not know what phase the project is in, since these measures are just a point in time. All projects would be subject to change in both schedule/cost as they move forward so with the information provided, it is indeterminate. (PMBOK 2013 Rev 5th Edition, pgs 217-225).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.