Skillset can help you prepare! Sign up for your free Skillset account and take the first steps towards your certification.
Observing the attached PDM diagram, how many days would it take to execute the project beginning to end? (Assume 1 week =7 days)
None of these
The total number of weeks to execute the project from beginning to end is 17 weeks and 2 days.
There is no diagram displaying
The total number of weeks to execute the project from beginning to end is 18 weeks.
The total number of weeks to execute the project from beginning to end is 12 weeks.
The total number of weeks to execute the project from beginning to end is 11 weeks and 4 days.
The correct answer is 12 weeks (11.71 weeks) to complete project beginning to end, critical path is items 1,2,3,5,8,12,13,14 and a week is equivalent to 7 days. (PMBOK 2013 Rev 5th Edition, pas 177-180). NO DIAGRAM WAS ATTACHED.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.