The Director of PMO has lost several key project managers in the last month. He has calculated the Schedule Performance Index of 7 projects. .5, .85, 1.4, 1.1, .65, 1.6, and .9. How many projects are ahead of schedule and how many are behind?
3 projects are behind and 4 projects are ahead of schedule.
None of the Above
3 of the projects are ahead of Schedule and 4 projects are behind.
All of the projects are behind
Let's first look at the definition of Schedule Performance Index; SPI is the ratio of earned value to planned value (EV/PV). A value of 1.0 indicates on schedule, A value <1.0 is behind schedule, and a value>1.0 is ahead of schedule. The correct answer is 3 project are >1 (ahead of schedule) while remainder are <1 or behind schedule.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.