The duration of schedule activities and costs of project components, which are used extensively in modeling and simulation, are called __________.
Probability distributions
Data gathering and representation techniques
Prioritized list of quantified risks
Sensitivity analysis
This is a standard definition used in the PMBOK Guide under Project Risk Management.