The process of developing a secure facility plan is called the critical path analysis. The critical path analysis is used to systematically identify critical operations and processes. Three of the following factors are most suited for the analysis of a server room. Which would not be a part of a critical path analysis?
Electrical reliability
Flood plain level
Temperature control
Cost of IT equipment upgrade
The correct answer is Cost of equipment upgrade. The remaining answers A, C, and D. are all correct parts of the critical path analysis. Cost of IT equipment upgrade does not affect facility security.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.