The Schedule performance index(SPI) is 0.8 and earned value is $100,000. What is the schedule variance if the total budget of $125,000 was used in this project?
-$25,000
$20,000
$23,000
-$20,000
SV (Schedule variance)=EV(Earned Value)-PV(Planned value), SPI=EV/PV.; 7.4.2.1 PMBOK Ed 5 Earned value management.