Three Point Estimation problem: Storage Shed Project (Start to Completion): Most Likely - 3 people/5 days; Pessimistic - 1 person/14 days; Optimistic - 5 people/2 days. What is the Activity Distribution TE?
7
5
4
8
6
TE = (To+(4TM)+Tp)/6 = (2+(45)+14)/6 = 6 days