What is a common technique of creating a schedule that prioritizes activities with no float?
none of the above
resource leveling
critical path method
schedule baseline
The Critical Path Method is a technique that uses the network diagram and durations to determine the earliest and latest activities that can start and finish in a project. Those activities with no float are said to be critical.