Which is NOT an input in the Activity Duration Estimating process?
Risk register
Basis of estimates
Activity resource requirements
Activity list
The answer is the correct choice according to the PMBOK Guide. Basis of Estimates, is an output of the PMBOK®’s Estimate Costs process. This is a companion document to Activity Cost Estimates, which details how much each project activity is expected to cost. The Basis of Estimates document indicates how these estimates were derived.