Which of the following are inputs to estimating costs?
Project Schedule
Stakeholder Register
Activity List
Risk Register
Scope Baseline
Scope Baseline, Risk Register and Project Schedule are all inputs for estimating costs. Activity List is used to develop schedule which is needed as an input to Estimate Costs. The Stakeholder Register is not needed to Estimate Costs.