Which of the following is a tool or technique in the estimate costs process?
Risk register
Reserve analysis
Enterprise environmental factors
Organizational process assets
This is a standard definition used in the PMBOK Guide under Project Cost Management under estimate costs process. The PMBOK defines reserve analysis as an analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.