Which of the following is NOT an objective of the Initiating Process Group?
Develop the Project Charter
Procure Goods
Identify internal and external stakeholders
Select the project manager
The objectives of the Initiating Process Group include: select project manager, authorize the project manager to apply organizational resources, authorize a project via a Project Charter, develop the Project Charter, and identify internal and external stakeholders.