Which of the following is not part of the cost baseline?
Management Reserve
Contingency Reserve
Procurement Costs
Resource Costs
Only the management reserve is left out of the cost baseline, and is also out of the hands of the project manager. To access the management reserve, the project manager must typically request permission from the sponsor or senior management.