Which of the following processes fall under Project Time Management?
Develop Schedule
All of the above
Estimate Activity Durations
Estimate Activity Resources
As per PMBOK (Pg 61), Estimate Activity Resources, Estimate Activity Durations and Develop Schedule all fall under Project Time Management.