Which of these is NOT an input to control procurement?
Work performance Information
Contracts
Work performance data
Agreements
Original Explanation - 12.5 PMBOK Control procurement Page 356, 5th ed / Revised Explanation - In the PMBOK Guide Page 492, Figure 12-6. Control Procurements: Inputs, Tools & Techniques, and Outputs show under the Inputs Table, 3. Agreements, 6. Work Performance Data where as under the Outputs Table, there is 2. Work Performance Information. Work Performance Reports are not found in any of the Tables. Correct Answers should be Work Performance Information and Work Performance Reports
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.