Who can approve of changes to any of the primary constraints on your project such as scope, budget, or timeline?
Key stakeholders
Project Staff
Sponsor (i.e. Senior management) or Customer
The Change Control Board
While the change control board might have approved the change request, certain changes may require approval from the customer or sponsor. Changing a primary constraint which impacts the functionality, cost or delivery time will normally need sponsor or customer approval. PMBOK 5th pg.96