You're managing a project, and you need to apply resource leveling. Which of the following tools can help you determine resources that are over-allocated?
Resource assignment matrix
Resource histogram
Resource breakdown structure
Network diagram
The resource histogram is a tool that is often used by the project management team and or as a means of providing a visual representation to the team and to all of those interested parties. Specifically speaking, the resource histogram is specifically a bar chart that is used for the purposes of displaying the specific amounts of time that a particular resource is scheduled to be worked on over a predetermined and specific time period. Resource histograms may also contain the comparative feature of resource availability, used for comparison on for purposes of contrast. Resource histograms are indeed handy tools to utilize for the project management team and or the project management team leader because they allow a quick and easy single page view of exactly what resources are available, what resources are being utilized at the present time (or at whatever time the project management team and of project management team leader is seeking information on), and how long those resources are expected to be tied up.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.