A project is under review and management has stated that quality is the highest concern. Use of the project management triangle would assist with deciding which of the following is the correct choice to make?
Increases in quality can be achieved, even if resource allocation is decreased.
Decreases in delivery time can be achieved, even if resource allocation is decreased.
Decreases in delivery time requires demand for quality is decreased.
Increases in quality requires resource allocation to be increased.
The triangle requires that quality is constant, thereafter changes to resource or time can occur but must ensure that if one if decreased the other is equally increased and vice versa!
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.