Alex, a project manager working on his first project, is preparing the outputs of the Direct and Manage Project Work process. One of the outputs is project document updates. Which of these is least likely to require updates as the result of the Direct and Manage Project Work process? (PMBOK 5th Edition pg 86 &94)
Requirements documentation
Schedule and cost forecasts
Risk register
Stakeholder register
Schedule and cost forecasts are more likely to be updates as part of the Monitor and Control Work process, not the Direct and Manage Project Work process. The project document updates most likely required by the Direct and Manage Project Work process are requirements documentation, project logs such as issues and assumption, the risk register, and the stakeholder register.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.