Calculating float to determine the least scheduling flexibility of project activities is measured by _______.
PERT
Critical Path Method (CPM)
GERT
Monte Carlo Analysis
Refer to the PMBOK Guide. CPM is the procedure of using a forward and backward pass to calculate the early start, early finish, late start, and late finish of the activities is the standard way to find out which activities are on the critical path.