The New Building Design Project to complete design and clear property sections is 8 weeks
The New Building Design Project to complete design and clear property sections is 2 weeks
The New Building Design Project to complete design and clear property sections is 10 weeks
The New Building Design Project to complete design and clear property sections is 6 weeks
None of these
There is a New Building Design Project, the critial path task is design and since clear property is only 2 weeks it has no influnce on overall duration so to complete these 2 tasks, is only 6 weeks. This tasks dependency is start of project. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.