A Project is started on a Monday, if we assume work is only conducted during weekdays, which of the following best represents when the foundation will be complete?
The Foundation will be completed in 18 work days
The foundation can begin building in 10 work days and the Basement can be dug 11 work days after project start
None of these
The Foundation can start being built in 3 work days
The Foundation can begin building in 10 work days
The Basement can be dug 11 work days after the project start
The Foundation will be completed in 15 days: 10 days for materials and 5 days to build.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.