Observing the attached PDM diagram, what items are on the critical path (assume 1 week = 5 days) from beginning to finish of project?
The critical paths items are 1,2,3,4,5,8,9,10,& 11.
The critical paths items are 1,2,3,4,5,6,7,10,& 11.
The critical paths items are 1,2,3,4,5,8,9, & 10.
None of these
The critical paths items are 1,2,3,4,5,8,9,& 11.
The correct answer is critical path is items 1,2,3,4,5,8,9,10, &11. (PMBOK 2013 Rev 5th Edition, pgs 177-180).