The project above involves developing and shipping a product. Based on the project flow above, which of the following scenarios is accurate?

The total project duration from project start to ship product complete in 6 weeks and the project duration from project start to beginning of test product in 4 weeks is correct

The project duration from design product completion through build product completion is 1 week

All of these are correct

The total project duration from project start to ship product complete is 6 weeks

The project duration from project start to beginning of test product is 4 weeks

Explanation

T42-Estimate Resource Activities ITTOs

Video Training

Train with Skillset and pass your certification exam. Faster. Guaranteed.

Directory

Skillset helps you pass your certification exam.

Contributions and Interactions
Practice Questions

Study thousands of practice questions that organized by skills and ranked by difficulty.

Contributions and Interactions
Personalized Training

Create a tailored training plan based on the knowledge you already possess.

Training Video Selector
Exam Readiness

Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.

Get A Free Skillset Account