In Planning Risk responses, which would be the first step?
Prioritize Identified Risks
Change Project Direction
Assign Responsibility for Risks
Allot Funding for the Risks
Determine Correct Strategy to Address Risk
The correct answer is Prioritize Identified Risks. The other steps would not be logical until the most likely and largest impact Risk to the project is identified.