Mora, an experienced project manager has gathered work performance data as an output of the Direct and Manage Project Work process. Which of the following would not be an example of work performance data she has gathered? (PMBOK 5th Edition pg 85 & 93)
Information Notes
Actual durations
Technical performance data
Number of change requests
Information notes are an example of a work performance report (an output of the Monitor and Control Project Work process), not work performance data. Work performance data is gathered through the execution of work and passed on to the controlling process for further analysis. Examples of work performance data include work completed, key performance indicators, technical performance data, start and finish dates of schedule activities number of change requests, number of defects, actual cots, and actual durations.
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.