The new product build will be unaffected by buying equipment unless timing exceed 6 weeks.
The new product build will be affected by buying equipment 4 weeks.
The New Product will be unaffected until buying equipment exceed 5 weeks.
The new product build will be affected by buying equipment by 2 weeks.
None of these
The New Product critical path does not include buying equipment unless it exceeds 6 weeks -so there is no effect on timing to begin build of product. This tasks dependency is having raw materials purchased and the unit designed. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.