Observing the attached PDM diagram, how many days (assuming a week = 5days) does this project take from beginning to element 9?
The total number of days to change critical path to 4,6, & 7 is >21 days.
The total number of days to change critical path to 4,6, & 7 is >21 days.
The total number of days to change critical path to 4,6, & 7 is >21 days.
The correct answer is 11 weeks ad 1 day to complete project beginning to element 9. (PMBOK 2013 Rev 5th Edition, pgs 177-180).