A Building Design project is started on a Monday, if we assume work is only conducted during weekdays and takes 6 weeks except for clearing property at 7 days per week, when will the building design and clearing of property be completed?
None of these
The New Building Design Project to complete design and clear property sections is 6 weeks
The New Building Design Project to complete design and clear property sections is 10 weeks
The New Building Design Project to complete design and clear property sections is 2 weeks
The New Building Design Project to complete design and clear property sections is 8 weeks
THIS IS INCOMPLETE!!!!! TheNew Building Design Project critial path task is design and since clear property has no influnce on overall duration to complete it doesn't matter if it is worked on at 7 days a week. The total duration of these 2 tasks, is still 6 weeks. These tasks dependencies are the design portion of project. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.